| Description |
Start Date |
End Date |
Hours |
| Horizontal Stabilizer |
March 13, 2001 |
April 15, 2001 |
48 |
| Vertical Stabilizer |
April 14, 2001 |
May 2, 2001 |
19.5 |
| Rudder |
May 6, 2001 |
June 1, 2001 |
27.25 |
| Elevators |
June 3, 2001 |
February 5, 2003 |
69.7 |
| Rudder II |
March 2, 2003 |
March 15, 2003 |
23.3 |
| Wings |
June 26, 2001 |
June 12, 2005 |
193 |
| Fuel Tanks |
August 20, 2001 |
July 2, 2005 |
94.95 |
| Ailerons |
November 25, 2001 |
February 24, 2002 |
38.5 |
| Flaps |
December 17, 2001 |
February 17, 2002 |
31.25 |
| Bulkheads |
March 6, 2002 |
April 21, 2002 |
48.05 |
| Aft Section |
April 21, 2002 |
August 14, 2003 |
44.55 |
| Forward Section |
May 25, 2002 |
May 7, 2003 |
118.45 |
| Top Fuselage |
August 20, 2002 |
March 13, 2005 |
90.95 |
| Cabin |
September 4, 2002 |
June 25, 2005 |
117.75 |
| Canopy |
October 16, 2002 |
June 27, 2005 |
154.2 |
| Fuel System |
February 22, 2003 |
November 2, 2003 |
25.95 |
| Fiberglass |
February 22, 2002 |
June 14, 2005 |
41.5 |
| Assembly |
February 6, 2003 |
June 26, 2003 |
50.9 |
| Electrical |
June 12, 2003 |
June 27, 2005 |
61.8 |
| Engine |
January 19, 2003 |
July 28, 2003 |
15.5 |
| FWF Misc |
July 29, 2003 |
June 26, 2005 |
89.8 |
| Cowling |
November 16, 2003 |
May 30, 2005 |
75.75 |
| Baffles |
February 13, 2003 |
April 5, 2004 |
64.2 |
| Panel |
April 16, 2004 |
March 21, 2005 |
128.85 |
| Finishing Up |
June 28, 2005 |
September 14, 2005 |
104.6 |
| |
| Project Totals |
| Days |
1647 | | Hours |
1778.25 | | Avg hours per day |
1.08 | Website Totals
| Logbook Entries | 755 |
| Logbook Chapters | 25 |
| Photos | 732 |
| Project Notes | 53 |
| Questions | 17 |
| Guestbook Entries | 453 |
|